Key milestones
Date | Progress |
---|---|
Summer 2019 – January 2020 | Keppel Street Phase 2b and c second-floor refurbishment designs completed and put to tender Tavistock Place new build construction preparations Refurbishments of the existing building at Tavistock Place |
January 2020 – Winter 2021 | Keppel Street refurbishments and creation of a new central services facility second-floor |
Winter 2020 | Tavistock Place enabling works complete |
Spring 2021 – Winter 2022 | Tavistock Place new build main works |
Spring 2022 | Keppel Street refurbishments complete, facilities in use |
Spring 2023 | Tavistock Place new build complete, staff and students move in |
We will seek to publish information about anticipated noisy works here. Please note works are subject to change and dates are indicative only.